1.           The Parish Council of Copmanthorpe have produced a Neighbourhood Plan for their area. This has been subject to an independent Examination following its formal Submission to the council.

2.           This report presents the conclusions of the Examination in the Examiner’s Report (Annex B) and recommends Executive to endorse the Examiner’s recommendations to enable the Neighbourhood Plan to proceed to Referendum, as set out in the Decision Statement (Annex C).

Benefits and Challenges

3.           The Copmanthorpe Neighbourhood Plan has been prepared by the Parish Council of Copmanthorpe and includes locally specific planning policies on issues important to the Parish. The Parish Council have worked collaboratively with the Council during the preparation to ensure it has been prepared in conformity with the Development Plan for the authority.

4.           This plan was prepared in advance of adoption of York’s Local Plan. However, all advice to the Parish Council has been based on the emerging Local Plan, including proposed modifications and the Examiner has taken this into account in his conclusions.

5.           Subject to Members’ decision to proceed, the decision as to whether the plan should be adopted is made by the Parish via a Referendum. If more than 50% of the vote is in favour, this plan will form part of the development plan for the authority’s area, together with the adopted Local Plan[1], other made neighbourhood plans, and the Joint Minerals and Waste Plan (2022[2]).

Policy Basis for Decision

6.           The Localism Act 2011 introduced new powers for community groups to prepare neighbourhood plans for their local areas.  The Neighbourhood Planning (General) Regulations 2012 (as amended) (“the Regulations‟) sets out the specific requirements for preparing the Neighbourhood Plan and bringing this into force as part of a development plan for the authority.

7.           The Regulations place a statutory duty on planning authorities to assist communities in the preparation of Neighbourhood Plans and to take plans through a process of Examination and Referendum. They also require decisions at key stages in the process within set time limits.

8.           Following receipt of the Examiner’s report, the legislation requires the Council to:

·                    Consider each of the recommendations made by the Examiner’s Report (and the reasons for them), and

·                    Decide what action to take in response to each recommendation.

9.           If the LPA is satisfied that the Neighbourhood Plan meets the Basic Conditions, is compatible with the Convention rights, and complies with the definition of an NP and the provisions that can be made by a NP or can do so if modified (whether or not recommended by the Examiner), then a referendum must be held. 

10.        The Council is required to publish its decision and its reasons for it in a ‘Decision Statement’. The Decision Statement must be published within 5 weeks beginning with the day following receipt of the Examiner’s Report unless an alternative timescale is agreed with the relevant Parish Council and / or its agents. In this instance, the Executive meeting falls outside the 5 week timescale – however, the Council has received written agreement from Copmanthorpe Parish Council that they agree to the extension of time to agree the Examiner’s Report and to agree to move on to referendum. Annex C presents the proposed Decision Statement required by Regulation 25 of the Neighbourhood Planning (General) Regulations (2012, as amended).

11.        The Examiner’s recommendations on the Neighbourhood Plan are not binding on the Council, who may choose to make a decision which differs from the Examiner’s. However, any significant changes from the Examiner’s recommendations would require a further period of public consultation, along with a statement from the Council setting out why it has taken this decision.

12.        As the Neighbourhood Plan is now at an advanced stage, its policies have legal weight in decision making with regard to any planning applications to be determined within the Copmanthorrpe Neighbourhood Plan area. This is reflected in The Neighbourhood Planning Act 2017 which recognises that, when determining an application, a LPA must have regard to “a post examination draft neighbourhood development plan as far as material to the application”. If a LPA makes a decision to allow a draft neighbourhood plan with modifications to proceed to referendum, then the modifications recommended must also be taken into account.

13.        The government have published guidance on the weight of the Neighbourhood Plan policies. The guidance states that ‘where the local planning authority has issued a decision statement (as set out under Regulation 18 of the Neighbourhood Planning (General) Regulations 2012) detailing its intention to send a neighbourhood plan to referendum, that plan can be given ‘significant weight’ in decision-making, so far as the plan is material to the application’.

14.        The Neighbourhood Plan supports the achievement of the core principles set out in the Council Plan. In particular, policies in the plan seek to support well designed development, as well as supporting green infrastructure with positive implications for health and well-being and climate change objectives.

Financial Strategy Implications

15.        The responsibility, and therefore the costs, of the Examination and Referendum stages of the Neighbourhood Plan production lie with the City of York Council. Table 1 below sets out a breakdown of the non-staffing costs of producing the Copmanthorpe Neighbourhood Plan to date and also sets out the estimated costs associated with the Examination and Referendum.

Table 1: Costs

Stage

Cost

Designation consultation

£500 (estimate)

Submission consultation

£500 (estimate)

NP grant to Parish Council

£3,000

Examination

Approx £3,000 exc VAT (final amount tbc)

Referendum

Circa £6,000 (tbc)

Total

£13,000 (estimate)

 

16.        A significant level of officer resources is required throughout the process to provide support to each of the Neighbourhood Planning Bodies during the preparation of the plan. This officer input seeks to ensure legal conformity, appropriate plan content, technical advice, including provision of mapping and assistance with Strategic Environmental Assessment (SEA) and Habitat Regulation Assessment (HRA).

17.        Financial support from Central Government is available for Local Planning Authorities (LPAs) involved with Neighbourhood Plans. £5,000 is available for the designation of five neighbourhood areas; York can no longer claim this as we have more than 5 designated neighbourhood areas. Local Planning Authorities can also claim £20,000 following a decision to proceed and setting a date for to referendum. A claim will be able to be made at the point when the local planning authority issues a Decision Statement detailing its intention to send the plan to referendum (rather than when a referendum date has been set) (Annex C).

18.        Copmanthorpe Parish Council was provided with a £3k grant from the Council to support the development of the neighbourhood plan to Submission.

19.        Communities with Neighbourhood Plans in place can also benefit financially should York adopt a Community Infrastructure Levy (CIL). They can benefit from 25% of the revenues from the CIL arising from the development that takes place in their area. At the Council’s Executive meeting on 26th January 2023, the Council made the decision to formally consult on the draft CIL Charging Schedule and associated Instalment Plan. In line with the CIL Regulations 2010 (as amended 2019), the CIL draft Charging Schedule was submitted for independent Examination on 18 July 2025. The examination hearing took place on 2 September 2025 and the CIL Charging Schedule is likely to be adopted by the end of the year.

 

Recommendation and Reasons

20.        It is recommended that Executive:

i)        Agrees the Examiner’s modifications set out at Annex C (Table 1) to the Submission Draft Copmanthorpe Neighbourhood Plan (Annex A) and that inclusive of those modifications the Neighbourhood Plan meets the Basic Conditions and other legislative requirements.

ii)       Agrees that the Submission Draft Copmanthorpe Neighbourhood Plan, as amended, proceeds to a local referendum based on the neighbourhood area as noted in the Examiner’s Report (Annex B). 

(iii)     Approves the Decision Statement attached at Annex C to be        published on the City of York Council’s website.

Reason: To allow the Neighbourhood Plan to progress in line with neighbourhood planning legislation.

 

(iv)    Agrees that delegated authority is given to the Director of City Development to approve and publish a Decision Statement in accordance with the statutory requirements:

(a)         should the outcome of the local referendum be in favour of adopting the Neighbourhood Plan, and the Copmanthorpe Neighbourhood Plan can be formally ‘made’; or

(b)         should the outcome of the local referendum not be in favour of adopting the Neighbourhood Plan, and the Copmanthorpe Neighbourhood Plan is formally rejected and the Plan cannot be made.

 

Reason: To conclude the Neighbourhood Plan process expediently.

 

Background

21.        The Copmanthorpe Neighbourhood Plan has been prepared by Copmanthorpe Parish Council, with engagement with the local community and City of York Council. Prior to Examination it has been through the following stages of preparation:

·        Area to be covered by Neighbourhood Plan submitted to City of York Council (September 2013);

·        Consultation on Neighbourhood Plan area (25 September 2013 to 6 November 2013);

·        Designation as a Neighbourhood Area (January 2014);

·        First Pre-Submission consultation Regulation 14 (September 2014);

·        Second Pre-Submission consultation Regulation 14 (May 2017);

·        Submission of Neighbourhood Plan to City of York Council (29 January 2025)

·        Submission Consultation – Regulation 16 (26 March 2025 -  14 May 2025).

22.        Following the close of submission consultation and with the consent of Copmanthorpe Parish Council, Andrew Ashcroft (BA(Hons), MA, DMS, MRTPI) was appointed to undertake an Independent Examination of the Neighbourhood Plan. The purpose of the Examination is to consider whether the Plan complies with various legislative requirements and meets a set of “Basic Conditions” set out in paragraph 8(2) of Schedule 4B of the Town and Country Planning Act 1990 as applied to neighbourhood plans by section 38A of the Planning and Compulsory Purchase Act 2004. The Basic Conditions are:

                     i.         To have regard to national policies and advice contained in guidance issued        by the Secretary of State;

                    ii.         To contribute to the achievement of sustainable development;

                  iii.        To be in general conformity with the strategic policies contained in the development plan for the area;

                  iv.        To not breach, and be otherwise compatible with, EU and European convention on Human Rights obligations; and

                   v.        To be in conformity with the Conservation of Habitats and Species Regulations 2017(3).

23.        The Examiner can make one of three overall recommendations on the Neighbourhood Plan namely that it can proceed to referendum (i) with modifications; (ii) without modification; or (iii) that the Neighbourhood Plan cannot be modified in a way that allows it to meet the Basic Conditions or legal requirements and should not proceed to referendum.

24.        Modifications can only be those that the Examiner considers are needed to:

a.   make the plan conform to the Basic Conditions

b.   make the plan compatible with the Convention rights

c.   make the plan comply with definition of a neighbourhood plan and the provisions that can be made by a neighbourhood plan or

d.   to correct errors. 

25.        If a recommendation to go to a referendum is made, the Examiner must also recommend whether the area for the referendum should go beyond the Neighbourhood Area, and if so what the extended area should be.

26.        The Regulations presume that Neighbourhood Plans will be examined by way of written evidence only, with a requirement for a hearing only in cases where the Examiner feels the only way to properly assess a particular issue is via a discussion with all parties. The Examiner decided that examination by written representations was appropriate in this case and provided his final report on 14 August 2025.

The Examiner’s Recommendations

27.        Annex B to this Committee report sets out the Examiner’s Report, which assesses the policies in the Neighbourhood Plan and makes a series of recommended modifications where necessary. It concludes that, subject to the modifications proposed, the Neighbourhood Plan meets the Basic Conditions required by legislation and that the Neighbourhood Plan should proceed to a referendum to be held within the Neighbourhood Area (based on the neighbourhood area as approved by the City of York Council on 7 January 2014).

28.        Positively the Examiner summarises that “I am satisfied that the content and form of the Plan is fit for purpose. It is distinctive and proportionate to the neighbourhood area. The wider community and CPC have spent time and energy in identifying the issue sand objectives that they wish to be included in their Plan. This sits at the heart of the localism agenda.”

29.        Officers have considered all the recommendations and the Examiner’s reasons for them and have set out the Councils response as part of the Decision Statement in Annex C.

30.        In summary, the Examiner has proposed modifications to the following policies:

·        CNP1 – Housing Quantity;

·        CNP2 – Design Principles;

·        CNP3 – Affordable and Special Housing;

·        CNP4 – Local Occupancy;

·        CNP5 – Community Facilities and Organisations;

·        CNP6 – Green Belt;

·        CNP7 – Green Infrastructure;

·        CNP8 – Parish Consultation;

31.        The Examiner also recommended modification of general text in the Plan, where required, to achieve consistency with the modified policies to accommodate any administrative and technical changes to ensure that the Plan is up to date. He also recommended that all references to the emerging Local Plan are updated to refer to the adopted Local Plan.

Next Steps - Referendum

32.        Should Member’s decide to endorse the conclusions of the Examiner’s report, the Council must organise a referendum on the Neighbourhood Plan. This ensures that the community has the final say on whether a Neighbourhood Plan comes into force. 

33.        The Regulations require the Local Planning Authority to hold a referendum within 56 days of the date that a decision to hold one has been made (excluding weekends and Bank Holidays). Subject to Executive endorsing the recommendations in this report, the referendum must be held by 24th December 2025. The date for the referendum and further details will be publicised following Executive’s decision.

34.    If over 50% of those voting in the referendum vote ‘yes’ in favour of the Neighbourhood Plan, then under the legislation the Council must bring it into force within 8 weeks of the result of referendum (unless there are unresolved legal challenges).

Consultation Analysis

35.        The overall process for creating a Neighbourhood Plan is collaborative between the qualifying body, in this case Copmanthorpe Parish Council and the Council. Preparation of the plan is undertaken by the qualifying body and is then submitted to the Council. After Submission of the plan, the Council leads on its independent Examination and subject to this being successful, the Referendum process.

36.        Paragraph 20 of this report sets out all of the stages of consultation that the Copmanthorpe Neighbourhood Plan has been through. A Consultation Statement prepared by the Parish Council was submitted with the Neighbourhood Plan setting out when and how consultation was undertaken in preparation of the plan’s submission to the Council.

37.        In accordance with Regulation 16, City of York Council carried out consultation on the Submitted version of Copmanthorpe Neighbourhood Plan between 26th March 2025 and 14th May 2025. This consultation was in accordance with the Council’s Statement of Community Involvement.

Options Analysis and Evidential Basis

38.        Options for Executive to consider are:

                     i.        Endorse the Examiner’s Recommendations, including the proposed modifications (Annex B) and approve the Decision Statement (Annex C).

                    ii.        Executive provide modified recommendations to those made by the Examiner and, if considered to be significant, agree that these will be subject to further consultation along with a statement explain why the decision differs from the Examiner’s.

                  iii.        Executive reject the Examiner’s recommendations and refuse the Neighbourhood Plan proposal.

                  iv.        Executive delegate authority to the Director of City Development to formally make, or reject, the Neighbourhood Plan in accordance with the outcome of the referendum and the publishing of a decision statement.

                   v.        Executive continue to consider the outcomes of the referendum prior to publishing a decision statement formally making, or rejecting, the Neighbourhood Plan.

39.        It is considered that, subject to the modifications proposed, the Neighbourhood Plan meets the Basic Conditions, is compatible with the Convention Rights and complies with the provisions that can be made by a neighbourhood plan. Consequently, Option (i) is recommended to enable the Copmanthorpe Neighbourhood Plan to proceed to Referendum.  Option (ii) is not considered to be justified given the plan meets the statutory requirements and is therefore not recommended.

40.         Option (iii) is also not recommended as it can only be justified if the Examiner recommends that the Plan should not proceed to a referendum, or the Council is not satisfied that the plan has met the procedural and legal requirements. A decision to refuse the Neighbourhood Plan proposal could only be made on the following grounds:

•        the LPA is not satisfied that the Neighbourhood Plan meets the Basic Conditions;

•        the LPA does not believe that with modification Neighbourhood Plan can meet the Basic Conditions;

•        the LPA considers that the Neighbourhood Plan constitutes a    repeat proposal; or

•        the LPA does not believe the qualifying body is authorised or     that the proposal does not comply with that authorisation.

This option would not be justified because the Examiner has identified that the Plan is sound and can proceed to referendum.

 

41.        The Local Planning Authority must ‘make’ the Neighbourhood Plan following a favourable vote at referendum. Consequently there is no decision for Executive to make at this stage other than to agree publication of the formal decision statement. To allow an expedient decision to be published, Option (iv), rather than option (v), is recommended.

Organisational Impact and Implications

42.         Financial: The examination and referendum will be funded by City of York Council. A claim by the City of York Council will be able to be made to government for a grant of £20,000 at the point the City of York Council issues a decision statement (as set out under Regulation 25 of the Neighbourhood Planning (General) Regulations 2012) detailing its intention to send the plan to referendum. The government grant of £20,000 can be put towards the costs of the City of York Council’s involvement in preparing the Plan (including the costs of the Examination and referendum). Any shortfall will need to be accommodated within existing resource.

43.       Human Resources (HR): There are no HR implications contained in this report. Should there be any requirement for additional resource by CYC in relation to the undertaking of the referendum, then these would be established and resourced in accordance with Council policy.

44.         Legal: The Legal implications are set out within the body of this report. A decision to proceed to referendum is, like all decisions of a public authority, open to challenge by judicial review. The risk of any legal challenge to the Neighbourhood Plan being successful has been minimised by the thorough and robust way in which it has been prepared and tested.

45.         Procurement: Should any outcomes from this report require procurement, all works and/or services must be procured via a compliant, open, transparent, and fair process in accordance with the council’s Contract Procedure Rules and where applicable, the Procurement Act 2023. Further advice regarding the procurement process and development of procurement strategies must be sought from the Commercial Procurement team. 

46.         Health and Wellbeing: Public Health endorses the proposal to accept the examiners recommendations, and the plan now proceeds to local referendum. Public Health supports the inclusion of well-designed, sustainable developments which meets the needs of local residents, and accessible green infrastructure and more emphasis on these points could be made within the plan. Public Health along with planning colleagues are developing a Healthy Places Supplementary Planning Document which will challenge developers to: prioritise Healthy Homes and affordability; active travel and accessibility; healthy environments and vibrant neighbourhoods. The use of the Rapid Planning for Health checklist and the Health Impact Assessment is recommended to be used for any development proposals made within Copmanthorpe.

47.        Environment and Climate action: Policies contained within the Copmanthorpe Neighbourhood Plan have limited scope to contribute towards the ambitions of the Climate Change Strategy. However, Policy CNP7: Green Infrastructure, may contribute to the promotion of biodiversity and enhancement of nature.

Other climate change and carbon reduction requirements are covered by policies in the Local Plan.

48.         Affordability: Communities with Neighbourhood Plans in place can benefit financially should York adopt a Community Infrastructure Levy (CIL). They can benefit from 25% of the revenues from the CIL arising from the development that takes place in their area bringing the opportunity to fund local community developments.

49.         Equalities and Human Rights - The EIA produced no likely significant impacts from the policies in the Neighbourhood Plan.

50.         Data Protection and Privacy:  The data protection impact assessment (DPIAs) screening questions were completed for the recommendations and options in this report and as there is no personal, special categories or criminal offence data being processed to set these out, there is no requirement to complete a DPIA at this time. However, this will be reviewed following the approved recommendations and options from this report and a DPIA completed if required.

51.         Communications: The Copmanthorpe Neighbourhood Plan comms will be contained to the announcement through Executive decision and reactive communications in response to media enquiries.

52.         Economy: The economy of Copmanthorpe is a due consideration of the development of the Copmanthorpe Neighbourhood Plan which has been led by the local community to meet the local community needs.

Risks and Mitigations

53.         In compliance with the Council’s risk management strategy, the main risk associated with the Copmanthorpe Neighbourhood Plan arise from failure to comply with the laws and regulations relating to Planning and the SA and Strategic Environmental Assessment processes and not exercising local control of developments.

54.         The Examiner’s conclusions state that he is satisfied that, with proposed modifications, the plan meets the statutory requirements and can proceed to the next stages. Overall risk associated with failure to comply is therefore deemed to be low.

Wards Impacted

55.         This Neighbourhood Plan relates to the Copmanthorpe Ward.

Contact details

 

For further information please contact the authors of this Decision Report.

 

 

 

 

 

 

 

 

Author

 

Name:

John Roberts

Job Title:

Strategic Planning Policy Officer

Service Area:

Strategic Planning Policy, City Development

Telephone:

01904 552255

Report approved:

Ben Murphy

Date:

12/8/25


Co-author

 

Name:

Alison Stockdale

Job Title:

Strategic Planning Policy Manager

Service Area:

Strategic Planning Policy, City Development

Telephone:

01904 552255

Report approved:

Ben Murphy

Date:

12/8/25


Background papers

 

Cabinet 07/01/14: Approval of Copmanthorpe Neighbourhood Plan application and boundary 

 

Officer Decision 12/02/2025: To write to Copmanthorpe Parish Council formally accepting the submission of the draft Copmanthorpe Neighbourhood Plan

 

Officer Decision 03/03/2025: To agree the consultation strategy for the Regulation 16 submission consultation on the draft Copmanthorpe Neighbourhood Plan

 

Dedicated webpage: https://www.york.gov.uk/planning-policy/copmanthorpe-neighbourhood-plan


Annexes

 

·        Annex A: Copmanthorpe Neighbourhood Plan (Submission version)

·        Annex B: Examiner’s Report

·        Annex C: Draft Decision Statement

·        Annex D: Equalities Impact Assessment (EIA)



[1] Adopted on 27 February 2025

[2] Jointly prepared with North Yorkshire and North York Moors and adopted on 27th April 2022.